The Establishment, Kangaroo Point

Full repaint of The Establishment, an eight level apartment building on Anglesey Street, Kangaroo Point, for the body corporate. The facade is painted from the ropes, so there is no scaffold around the building and residents keep their views and their balconies for most of the job.

Scope: wash down, the exterior walls and wall tops from the ropes, every balcony zone by zone and level by level, then the internal hallways from the top floor down. Waterproofing and sealant at the wall tops are done before the paint goes on.

How it is run: the building is split into zones so only a small group of balconies is closed at a time. Residents get a notice before their zone starts, and the body corporate, project manager and building manager get a written progress report with photos. Hallways are done in a low odour acrylic, ceilings and walls first.

Program: started 30 August 2026, about 24 weeks.

In Progress

Rope access crew on the roof edge of The Establishment, Kangaroo Point
Ropes rigged down the facade of The Establishment, Kangaroo Point
Rope lines down the side wall of The Establishment, Kangaroo Point
Painting a balcony from the ropes at The Establishment, Kangaroo Point
Freshly painted balcony edge at The Establishment, Kangaroo Point
Ground level walls at The Establishment, Kangaroo Point

Got a building like this?

Tell us about it. We will come out, have a look and send a written quote.